34. Towers Perrin was appointed Investment Consultant of 
                      the Trust Fund pursuant to Orders of the Courts. The Joint 
                      Committee recommends the continuation of this appointment.
                    35. Attached hereto and marked as Schedule 
                      "K" is a letter dated May 1, 2001 from Towers 
                      Perrin summarizing their activities for the fiscal year 
                      ended March 31, 2001. Attached and marked as Schedule 
                      "L" is a copy of the Executive Summary of 
                      the annual report of Towers Perrin which has been provided 
                      to the Joint Committee.
                    36. The Courts approved an annual budget for Towers Perrin 
                      in the amount of $56,004.00. The actual expenses of Towers 
                      Perrin for the year ended March 31, 2001 were the budgeted 
                      amount. 
                    37. Towers Perrin proposes and the Joint Committee recommends 
                      that its budget for the year commencing April 1, 2001 and 
                      ending March 31, 2002 be $56,000.00 plus GST. This proposed 
                      budget is set out in Schedule 
                      "K".
                    